Why there were no trains at King’s Cross over Christmas

WEEKLY NEWSLETTER SIGN UP

No trains were able to access King’s Cross station over Christmas 2020 for one simple reason – there was no track for them to run on.

The Camden Sewer runs under the tracks in the station throat.  It is old and quite close to the surface, necessitating a speed restriction over the top of it.

The ends of the King’s Cross platforms are at the top of this photo. Hollow blocks to construct the new sewer are on the left.

Christmas 2020 was the time chosen to replace it. So, the railway was closed, the tracks removed, and a massive trench dug to allow for the installation of the new sewer, constructed from precast concrete blocks and set deeper into the ground. The old sewer was removed at the same time.

The first train out of the partially reopened station on 31 December 2020.

The first stage was complete by 31 December, allowing the station to partially reopen, and work continued to finish off the rest by 4 January.

Work to install overhead contact wires in Gasworks tunnel continued.

At the same time, while there were no trains running, work continued to bring the third bore of the Gasworks tunnel, with its freshly laid slab track, back into use to ease congestion on the approach to King’s Cross.

All in all, it was a productive Christmas/New Year break.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisement -

Latest news

Fatal rail accident in Montana, USA

On Saturday 25 September, Amtrak’s Empire Builder train 7/27, operating a service between Chicago and Seattle/Portland, Oregon, derailed at around 16:00 local time near...

One of the worst staff incidents in UK rail history remembered 100 years on

Sunday marked the centenary of one of the most fatal trackside incidents in the history of UK rail. The incident saw five killed and another...

Rail engineers strike gold in sustainability school

Multidisciplinary engineering business Dyer & Butler has earned Gold level status from the Supply Chain Sustainability School (SCSS). This is the highest level of membership...
- Advertisement -

More news

Tunnel operation takes flight with help from a helicopter

Essential work on a tunnel in the Peak District got some help from high places. Helicopters helped airlift construction materials into position as part of...

Island Line to re-open this autumn

South Western Railway has said that the Island Line is set to reopen on 1 November. The upgraded line’s reopening is subject to a final...

Rail review author calls for rail fares reform

Keith Williams, co-author of the Williams-Shapps Plan For Rail white paper, has urged for fares reform – arguing there has never been a better...
NEWSLETTER SIGN UP