HomeInfrastructureGeotechnicalLine reopens after Ashford landslip prevention works

Line reopens after Ashford landslip prevention works

WEEKLY NEWSLETTER SIGN UP

The Ashford line, between Maidstone East and Ashford International in Kent, has reopened after work to prevent landslips was carried out during a nine-day closure.

Network Rail estimated that the improvements cost £10 million as it worked with contractors BAM to repair and reinforce steep sides of a cutting near Bearsted. The area is so prone to landslips and rock falls that one even took place while the stabilisation work was underway.

Work included drilling soil and rock nails deep into the ground on either side of the line, and pumping grout around them to hold the sides of the cutting together. In total, engineers installed 1,100 rock bolts and 500 nails into the cutting and drilled a total of 6,800 metres of bolt holes.

Netting along the top will hold looser material in place and stop rock and soil being washed onto the railway during heavy rain.

The steep sides of the cutting at Bearsted have now been stabilised to prevent rock falls.

While the line was closed, Network Rail also carried out other work, including painting at stations along the line and improving the electrical supply to trains by laying new cables.

Fiona Taylor, Network Rail.

Network Rail’s route director for Kent, Fiona Taylor, said: “This was a massive job for us and for our neighbours and passengers and we really appreciate their patience. The section of line between Maidstone East and Bearsted was a big worry, with two rock falls in recent years and another one last week. The work we’ve done over the past nine days has helped make it much safer.

“We don’t get to close railways very often, so we took advantage of the time to do lots of other work, from laying new cables to painting bridges, railings and roofs, and even jet washing platforms.

“We’ve got a bit more to do in the coming weeks, so our neighbours will still see us around, but passengers will be pleased to hear that trains are running again.”

Scott Brightwell, Southeastern.

Southeastern train services director, Scott Brightwell, added: “I want to say a big thank you to all our passengers for bearing with us while this essential repair work was carried out.

“Reducing the risk of landslips across our network is an important part of providing a reliable service. We also took the opportunity to make some station improvements while the line was closed and I hope our customers are pleased with what they see.”

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisement -

Latest news

Rail engineers strike gold in sustainability school

Multidisciplinary engineering business Dyer & Butler has earned Gold level status from the Supply Chain Sustainability School (SCSS). This is the highest level of membership...

Tunnel operation takes flight with help from a helicopter

Essential work on a tunnel in the Peak District got some help from high places. Helicopters helped airlift construction materials into position as part of...

Island Line to re-open this autumn

South Western Railway has said that the Island Line is set to reopen on 1 November. The upgraded line’s reopening is subject to a final...
- Advertisement -

More news

Rail review author calls for rail fares reform

Keith Williams, co-author of the Williams-Shapps Plan For Rail white paper, has urged for fares reform – arguing there has never been a better...

Iconic arrows get a dash of green ahead of environmental summit

The famous National Rail double arrow has turned several shades of green ahead of the COP26 UN climate summit, which takes place in November. The...

Digital signalling for East Coast main line tested on Thameslink

A test of the digital in-cab signalling system ECTS level 2 (European Train Control System) has been carried out successfully using a Govia Thameslink...
NEWSLETTER SIGN UP