Harbury revisited

WEEKLY NEWSLETTER SIGN UP

An extensive cutting face alongside the Chiltern main line in Warwickshire has been stabilised to remove the threat of landslips that could block the line.

On 31 January 2015, 350,000 tonnes of earth moved on the north side of Harbury tunnel, forcing the route between the Midlands and London to close for six weeks.

This was only the latest problem at Harbury. Ground conditions in the area have caused problems for the railway ever since it was built in 1852, and engineers from the Great Western Railway made the slopes of the cutting at Harbury shallower to prevent landslips as far back as in 1884.

Having stabilised the cutting at the north end of the tunnel following the slip in 2015, Network Rail and its contractors started to work on the cutting at the southern end in December 2019. The £9 million project took 15 months to complete, and work finished on 5 March 2021.

350,000 tonnes of material slipped by up to four metres at the north end of Harbury tunnel in 2015, closing the railway for six weeks.

Emma Gray, scheme project manager at Network Rail, explained: “The ground here, made up of layers of limestone and shale, can be unstable and could potentially cause issues for the railway running through it. This preventative work will stop future slips and make it much more secure.

“We know Harbury very well after the huge landslip in 2015, and I want to thank the local community for their patience while we carried out this important work to protect the railway.”

All finished! The southern cutting at Harbury in March 2021.

Soil nails and piles were driven into the slopes to stabilise them and a new retaining wall was built at the bottom of the railway cutting to prevent soil movement. The work was carried out during the daytime, while passenger and freight trains continued to run below, meaning no disruption to services and no noisy overnight work.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisement -

Latest news

Rail engineers strike gold in sustainability school

Multidisciplinary engineering business Dyer & Butler has earned Gold level status from the Supply Chain Sustainability School (SCSS). This is the highest level of membership...

Tunnel operation takes flight with help from a helicopter

Essential work on a tunnel in the Peak District got some help from high places. Helicopters helped airlift construction materials into position as part of...

Island Line to re-open this autumn

South Western Railway has said that the Island Line is set to reopen on 1 November. The upgraded line’s reopening is subject to a final...
- Advertisement -

More news

Rail review author calls for rail fares reform

Keith Williams, co-author of the Williams-Shapps Plan For Rail white paper, has urged for fares reform – arguing there has never been a better...

Iconic arrows get a dash of green ahead of environmental summit

The famous National Rail double arrow has turned several shades of green ahead of the COP26 UN climate summit, which takes place in November. The...

Digital signalling for East Coast main line tested on Thameslink

A test of the digital in-cab signalling system ECTS level 2 (European Train Control System) has been carried out successfully using a Govia Thameslink...
NEWSLETTER SIGN UP