Line reopens after Ashford landslip prevention works

WEEKLY NEWSLETTER SIGN UP

The Ashford line, between Maidstone East and Ashford International in Kent, has reopened after work to prevent landslips was carried out during a nine-day closure.

Network Rail estimated that the improvements cost £10 million as it worked with contractors BAM to repair and reinforce steep sides of a cutting near Bearsted. The area is so prone to landslips and rock falls that one even took place while the stabilisation work was underway.

Work included drilling soil and rock nails deep into the ground on either side of the line, and pumping grout around them to hold the sides of the cutting together. In total, engineers installed 1,100 rock bolts and 500 nails into the cutting and drilled a total of 6,800 metres of bolt holes.

Netting along the top will hold looser material in place and stop rock and soil being washed onto the railway during heavy rain.

The steep sides of the cutting at Bearsted have now been stabilised to prevent rock falls.

While the line was closed, Network Rail also carried out other work, including painting at stations along the line and improving the electrical supply to trains by laying new cables.

Fiona Taylor, Network Rail.

Network Rail’s route director for Kent, Fiona Taylor, said: “This was a massive job for us and for our neighbours and passengers and we really appreciate their patience. The section of line between Maidstone East and Bearsted was a big worry, with two rock falls in recent years and another one last week. The work we’ve done over the past nine days has helped make it much safer.

“We don’t get to close railways very often, so we took advantage of the time to do lots of other work, from laying new cables to painting bridges, railings and roofs, and even jet washing platforms.

“We’ve got a bit more to do in the coming weeks, so our neighbours will still see us around, but passengers will be pleased to hear that trains are running again.”

Scott Brightwell, Southeastern.

Southeastern train services director, Scott Brightwell, added: “I want to say a big thank you to all our passengers for bearing with us while this essential repair work was carried out.

“Reducing the risk of landslips across our network is an important part of providing a reliable service. We also took the opportunity to make some station improvements while the line was closed and I hope our customers are pleased with what they see.”

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisement -

Latest news

Improvements carried out on major London route

A revamp of 1980s signalling systems over the weekend saw services stopped temporarily between London Victoria and East Croydon. Trains were diverted to London Bridge...

Northern takes control of major rail facility

Northern has confirmed it now has full control of Neville Hill depot in Leeds. Previously, the depot – along with its 550-strong staff of engineers,...

HS2 trains to be built in UK – but by whom?

German train maker Siemens has launched a legal challenge to HS2 awarding its rolling stock contract to a joint venture of Hitachi Rail and...
- Advertisement -

More news

Operator appeals for more considered use of emergency alarms

Passengers hitting the emergency alarms have cause 17 hours of delay in only half a year for one operator. From 1 April to 4 September...

Rail safety cyber security expert lands professor role

Rail safety cyber security specialist Dr Emma Taylor has taken up the role of visiting professor at Cranfield University. The appointment involves lecturing in the...

Night Tube set to return next month

After being suspended because of the pandemic, Transport for London (TfL) has said that the Night Tube is set to make a comeback in...
NEWSLETTER SIGN UP