Emergency work on four bridges will close the line between Ely and Peterborough for 28 days

WEEKLY NEWSLETTER SIGN UP

The line between March and Peterborough will be closed for several weekends later this summer and early autumn so that Network Rail can replace 87 pairs of wheel timbers on four bridges at Manea, Cambridgeshire.

Although 13 pairs of timbers were replaced on two bridges over Christmas 2017, a recent inspection showed that that 87 of the 140 pairs of wheel timbers across the four  structures now require urgent replacement.

Inspections were carried out on railway bridges with softwood timbers using new technology, to understand the internal condition of the timbers. This followed a derailment on 23 January 2020 at Wanstead Park on the Gospel Oak to Barking line, when a freight wagon damaged over two miles of track and eight bridges. 

Damage to bridge timbers on the Gospel Oak to Barking line caused by a derailed freight wagon in January 2020.

Although the cause of the derailment has not yet been officially confirmed, Network Rail inspected other bridges with similar timbers. The four bridges at Manea were part of this additional inspection programme, and the timbers were found to be in need of replacement. A 20mph temporary speed restriction is in place until the wheel timbers can be replaced.

The work is expected to be completed during a 28-day closure of the line from 6 September to 4 October 2020 and on five additional weekends from August until November.

Ellie Burrows, Network Rail.

Ellie Burrows, Network Rail’s route director for Anglia, said: “I know this kind of disruption is incredibly frustrating for our passengers, and I’m sorry that it will impact people’s journeys for so long.

“Running a safe railway is my absolute priority, and so while I know it will be painful for passengers and our freight customers, I believe this is the right decision to get the work done as soon as possible.”

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisement -

Latest news

Improvements carried out on major London route

A revamp of 1980s signalling systems over the weekend saw services stopped temporarily between London Victoria and East Croydon. Trains were diverted to London Bridge...

Northern takes control of major rail facility

Northern has confirmed it now has full control of Neville Hill depot in Leeds. Previously, the depot – along with its 550-strong staff of engineers,...

HS2 trains to be built in UK – but by whom?

German train maker Siemens has launched a legal challenge to HS2 awarding its rolling stock contract to a joint venture of Hitachi Rail and...
- Advertisement -

More news

Operator appeals for more considered use of emergency alarms

Passengers hitting the emergency alarms have cause 17 hours of delay in only half a year for one operator. From 1 April to 4 September...

Rail safety cyber security expert lands professor role

Rail safety cyber security specialist Dr Emma Taylor has taken up the role of visiting professor at Cranfield University. The appointment involves lecturing in the...

Night Tube set to return next month

After being suspended because of the pandemic, Transport for London (TfL) has said that the Night Tube is set to make a comeback in...
NEWSLETTER SIGN UP