3,000 hours of work make railway at Euston more reliable in hot weather

WEEKLY NEWSLETTER SIGN UP

Overhead contact wires have been overhauled and replaced outside London Euston station to make the railway more reliable in hot weather.

Tensioners were fitted to keep wires from sagging in hot weather,

A total of 3,000 hours of work over four weeks, mostly overnight, has resulted in 1,900 metres of new wires being installed. New overhead line equipment, which holds the new wires to the correct tension, has also been fitted.

James Dean, Network Rail.

James Dean, Network Rail’s route director for the West Coast main line South, said: “During extremely hot weather, overhead wires can sag. The wires can then catch on passing trains and be torn down.

“With extremes in temperature now becoming more common in Britain, we need to weather-proof our railway. This work is part of that.

“It will help stop cables sagging and reduce the risk of them coming down, making the West Coast main line more reliable for the tens of thousands of passengers travelling in and out of Euston every day.”

Gus Dunster, Avanti West Coast.

Gus Dunster, executive director of operations and safety with train operator Avanti West Coast, said: “We are pleased to have played a part in supporting Network Rail’s vital work to the overhead lines at Camden and would like to thank our customers for their patience, as we did our best to keep them moving.

“This essential work is the latest example of our collaboration with Network Rail to deliver additional maintenance projects while the railway is not operating at full capacity. The renewal of infrastructure and equipment on the approach to London Euston station will improve the reliability for millions of customers across the West Coast main line when we look forward to welcoming them back.”

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisement -

Latest news

Boost for regional transport in upcoming budget

It looks likely that Chancellor Rishi Sunak will announce a £5.7 billion investment into sustainable transport settlements for city regions in his Autumn Budget...

TSSA members vote to accept ScotRail pay offer

The TSSA has called off its dispute with ScotRail, with its members having voted to accept a new pay offer. The TSSA says the offer...

Passengers give rail a thumbs up in latest survey

Nearly ninety per cent of rail passengers said they were satisfied with their last journey, according to a new survey by watchdog Transport Focus. The...
- Advertisement -

More news

Rail museum holds consultation on major plans

The National Railway Museum will house a consultation on plans for a new Central Hall as part of its vision as the cultural heart...

TfL bodycam video results in assault conviction

Uxbridge Magistrates have sentenced a woman to a 12-month community order and 35 rehabilitation activity requirement days following a physical assault on two Transport...

Portishead line reopening delayed

A decision as to whether the Portishead line will return to life has been delayed by the government. North Somerset District Council had applied for...
NEWSLETTER SIGN UP